12 Month Action PlanĀ
September 2018 – October 2019
12 Month Action Plan | Responsibility | Timescale | Status |
Strengthen KRT’s internal systems, quality standards, processes and policies | CEO | December 2018 | Matrix Quality Standard awarded Oct 2018 |
Establish and launch KRT’s Social Enterprise Arm | Development Coordinator/Trainer | October | Social Enterprise commenced Oct 18 with a domestic gardening service |
Gain the Matrix Quality Standard in Information Advice and Guidance. | CEO | September 2018 - | Achieved |
Launch full commercial gardening service through KRT Social Enterprise | CEO /Development Coordinator/Trainer | April 2019 | Achieved |
Launch full Handy-Person service through KRT Social Enterprise | CEO /Development Coordinator/Trainer | August 2019 | Commenced Apr 2019 |
Become accredited CITB Training Organization | CEO | October 2018 | Achieved Dec 18 |
Establish and launch the North Birmingham Development Trust | CEO | October 2019 | In progress |
Deliver six environmental partnership projects | Development Coordinator | December 2018 | Achieved |
Develop IAG Career service for adults | Development Coordinator | April 2019 | Achieved |
Building asset transfer | Senior Trainer | December 2019 | In progress |